FIRST BLAST SIGNALS START OF SHAFT SINKING PHASE AT WESIZWE’S
Bakubung Platinum Mine (formerly known as Frischgewaagd-Ledig)
26 April 2011
Following the approval by Wesizwe shareholders in March 2011 of the total mine
development financing solution offered by the Chinese consortium of Jinchuan, CAD
Fund and Micawber, TWP Projects has submitted a full EPCM proposal to the company
for the new twin vertical shafts (the Main and Ventilation Shafts), a new plant and all
surface infrastructure at its Bakubung Platinum Mine (formerly known as Frischgewaagd-Ledig) near Rustenburg. This will be
concluded once a project approval is given by the Wesizwe board.
TWP’s involvement with Wesizwe spans back to 2006 when it conducted the prefeasibility
study. A full Bankable Feasibility Study (BFS), which was started in February
2007 and completed in June 2008, indicated the Bakubung Platinum Mine (formerly known as Frischgewaagd-Ledig) has the
resources to sustain a 35 year life-of-mine (LOM), with a total PGM production of
330 000 oz per annum. TWP is currently wrapping up the first phase of the EPCM
project scope which entailed access routes, fencing, the Eskom terrace, the Phase 1
pollution control dam, the Main and Ventilation Shafts terraces (excavating the box-cuts
on both shafts), surface drainage and the environmental berm as well as earthworks.
“The first blast represents a momentous milestone for Wesizwe,” says Wesizwe CEO,
Mr Arthur Mashiatshidi. “It is not common for exploration companies to take a project of
this magnitude from exploration to production. Usually a mining major will take over the
production after the exploration phase is concluded. In the case of Frischgewaagd-Ledig,
Wesizwe will develop it into an operating mine, and the first blast signals the start of the
long-awaited execution phase.”
Attended by executive representatives from Wesizwe, TWP and Scribante Construction,
the first blast to establish the box cuts of the Main and Ventilation Shafts took place on
5 April 2011. BENCO Engineering conducted the blasting using underground emulsion
charging units to open the ground. 460 detonators were positioned at a depth of 10m at
the Main Shaft, and 135 detonators in 6m holes at the Ventilation Shaft. The two blocks
were electronically detonated at the same time. Blast monitoring was conducted by Blast
Management & Consulting with readings taken as the blasts were set off to measure the
strength of any shock wave transmission from the point of detonation to the nearby
houses and structures. This was to ensure that data was captured accurately to confirm
the blast performance, aimed at minimal or no damage to any structure outside the
blasting circle, as determined by the blasting specialists.
“The next step is to begin with civil works – collaring on the box cuts to stabilise the top
10m on the shafts, before the start of the pre-sink activities in nine months’ time,” says
TWP project manager Jacob Mothomogolo. “The sinking will be one of the largest ticket
items of the project, with an estimated 17-18% of the total capital allocated to it. The presink
or slow sink on the shafts will be developed at a rate of 0,5m a day for up to six
months, until a depth of about 80m is reached. At that time, we will switch over to a
permanent set-up, including the installing of sinking winders, sinking headgears and
establishing a power connection with Eskom. The sinking of both the Main Shaft and the
Ventilation Shaft will be conducted simultaneously, with the former reaching a depth of
1 140m, and the latter a depth of 980m. The shafts will be 120m apart and will
interconnect at certain levels,” says Mothomogolo.
The sinking phase, including equipping and commissioning of shafts, is expected to be
completed within 62 months, at which time production build-up will begin and the capital
footprint established. This will involve infrastructure development, tunnels, ore passes
and any other excavation necessary to open up the resource block. The build-up period
will also see TWP preparing for client handover with the establishment of a full mining
operations team and personnel, and skills transfer by contractors to the permanent mine
workforce. The mine will require approximately 3 200 people at full production. With the
mine located in an established mining region, a skills survey indicated that there is
currently a requirement to train local employment seekers if the mine is to meet its SLP
commitment to sourcing most of its employees from the host and surrounding
communities. Certain specialist skills may have to be brought it from the active mining
sector outside the region.
It is expected that the mine will reach steady state production of 230 000 tonnes of ore
per month (180 000 tonnes of Merensky reef / 50 000 tonnes UG2 reef) within four to
five years’ time from start of build-up period. view gallery...
<< Go back |